GERMANY Law and Practice Contributed by: Katharina Spenner, Philipp Schütt, Joachim Fröhlich and Hannah Mack, Baker McKenzie

To successfully invoke relief from performance due to such a force majeure/impossibility event, the following conditions must generally be met: • the event must render the performance objectively impossible, not merely more difficult or economi - cally burdensome; • the event must be beyond the control of the obligated party and not attributable to any fault or negligence on their part; and • the obligated party must demonstrate that it made all reasonable efforts to fulfill the contract but was prevented from doing so due to the force majeure event. Additionally, force majeure events may be addressed through the doctrine of frustration of contract (Sec - tion 313 BGB), allowing for contract adjustment or termination when fundamental circumstances that both parties relied upon have significantly changed It is standard practice in German commercial con - tracts to include a force majeure clause. Such claus - es typically define what constitutes force majeure, specify the legal consequences (eg, suspension or termination of the contract), and set out notification requirements. The absence of a force majeure clause does not pre - vent a party from relying on the statutory provisions of German law (in particular, Section 275 BGB). Also see 6.1 Concept of Force Majeure . 6.3 Concept of Hardship German law recognises the concept of “frustration of contract” ( Störung der Geschäftsgrundlage ), in Sec - tion 313 BGB. If, after conclusion of the contract, unforeseen circumstances fundamentally change the basis of the contract and it would be unreasonable to hold a party to the original terms, that party may request an adjustment of the contract or, in excep - tional cases, termination. This applies only if the risk was not allocated to one party and the change is sub - stantial. The key requirements are: after the contract was concluded. 6.2 Force Majeure Clauses

• a shared or evident assumption forming the basis of the contract; • a serious and unforeseeable change in those cir - cumstances; and • the resulting unreasonableness of expecting one party to adhere to the original contract terms. 6.4 Hardship Clauses In Germany, commercial contracts – especially those with international scope – often contain hardship clauses, although such provisions are not legally required to access statutory remedies. This clause is generally included to provide mechanisms for rene - gotiating the price or other relevant elements of the agreement in good faith, in order to periodically update the price (in contracts on an ongoing basis) based on price indices (eg, published by the German Federal Statistical Office) or to restore balance following an unforeseeable situation. Importantly, the absence of a hardship clause does not bar a party from seeking legal remedies due to excessive burden arising after the contract was formed. 7. Warranties and Remedies 7.1 Warranties and Remedies Under Local Law German law provides a structured system of statutory warranties ( Mängelrechte ), particularly in sales con - tracts (Section 434–437 BGB), in case a product or work is defective. A defect can be a material defect (Section 434 BGB) whereby a good is defective if it does not have the agreed quality or is unsuitable for its usual or contractual purpose or a legal defect (Section 435 BGB) which exists if third-party rights interfere with the buyer’s use or ownership. If a defect exists, the buyer may demand: • subsequent performance (Section 439 BGB); • price reduction (Section 441 BGB); • withdrawal from the contract (Section 323 BGB); or • damages (Section 280, 281 BGB). For general breaches of contract, including delayed performance (Section 286 BGB) or impossibility (Sec -

226 CHAMBERS.COM

Powered by