ITALY Law and Practice Contributed by: Giacinto Zampetti, Andrea Cicala, Alessia Raimondo and Gaetano Iorio Fiorelli, Baker McKenzie

6.2 Force Majeure Clauses It is standard practice in Italy for commercial contracts to include a force majeure clause. If the contract does not contain a clause listing force majeure events and regulating relevant consequenc - es, the parties may invoke the general principles and remedies regarding “supervening impossibility” or “excessive economic burden” under Italian law, which may apply. 6.3 Concept of Hardship Although Italian law does not expressly regulate the theory of hardship (ie, the obligation to renegotiate the contract to restore the balance of the contract ( sinal- lagma ), it does recognise a similar concept: super - vening excessive onerousness ( eccesiva onerosità sopravvenuta ). Pursuant to Article 1467 of the Civil Code, in con - nection with agreements to be performed on a con - tinuous or recurring basis, or otherwise providing for a deferred term, if a party’s performance becomes excessively burdensome due to extraordinary and unforeseeable events (unidentifiable at the time the contract was concluded), that party may claim termi - nation of the agreement, unless the other party can avoid this by offering to revise the terms to re-achieve fairness. Under Italian law and based on the principles of con - tract preservation and good faith, a party facing termi - nation has the opportunity to prevent it by modifying the agreement terms to restore balance. However, unlike the Unidroit Principles, Italian law leaves any assessment of the economic balance of the parties’ obligations to their negotiating autonomy (Article 1322 of the Civil Code), which is unquestionable by the court. The termination remedy is not available in case the hardship falls within the risk normally associated with the nature of the agreement. It does not apply to agreements that are inherently “aleatory contracts” or where the parties have accepted the risk.

Nonetheless, the general concept used to describe situations like those falling within force majeure is essentially reflected in the notion of supervening impossibility ( impossibilità sopravvenuta ) which pro - vides, inter alia, that an obligation fades when the relevant performance becomes impossible due to a cause not attributable to the same debtor (Article 1256 of the Civil Code). Article 1218 of the Civil Code releases a party from its damage-related liabilities for non-performance of its obligations if it proves that such non-performance (or delay in performing) is due to an event not imputable to them. A party released from an impossible obligation cannot demand performance from the other party. In a nut - shell, the agreement would terminate with full release of the parties (Article 1463), however, if the perfor - mance becomes only partially impossible, the creditor has the right to either withdraw from the contract (if they do not have a notable interest in a partial per - formance) or to a corresponding reduction of its own counter-performance (Article 1464). Italian case law states that, to successfully claim force majeure as a relief from performance, there must be a specific impediment to performing a particular action, which should: • neutralise any efforts of the acting party aimed at overcoming such event; and • not be attributable to the acting party in any way. In other words, a force majeure event may be defined as an event or situation which is (i) extraordinary, (ii) unforeseeable (at the time of entering into the con - tract), and (iii) of such force as to make performance impossible, in whole or in part, and not simply more onerous. As an additional condition to invoke force majeure, the debtor must of course prove all the above circum - stances, including that the impossibility to perform occurred and that such impossibility is not attribut - able to them. Thus, the debtor must prove to have diligently endeavoured to perform, but failed with no fault, as an external event prevented the proper fulfil - ment of a given contractual obligation.

258 CHAMBERS.COM

Powered by