A party may be released from its obligations if it proves that: • the event was unforeseeable at the time of con - tracting; • it was beyond the party’s control; and • it made performance absolutely impossible, not merely more difficult or costly. When these conditions are met, the debtor is exoner - ated from liability and the obligation is extinguished. The affected party must also act in good faith, which includes: • promptly notifying the other party of the occur - rence of the event and its effects; • taking reasonable measures to avoid or mitigate the consequences; and • resuming performance once the impediment ceases, where possible. Thus, Moroccan law recognises force majeure as a general principle, offering relief even if the contract is silent on the matter, provided these prerequisites are met – although courts interpret this concept very strictly. 6.2 Force Majeure Clauses It is standard practice for commercial contracts in Morocco to include a force majeure clause providing relief from performance in circumstances beyond a party’s control, expressly defining what constitutes a force majeure event (such as natural disasters, gov - ernment actions or wars) and outlining the procedure for notification and suspension or termination of obli - gations. That said, the force majeure clause should be included within the definition of force majeure as set out in the DOC. However, the absence of such a clause does not prevent a party from claiming relief under Moroccan law. This is because the principle of force majeure is already recognised under the DOC. In other words, even if the contract does not contain a force majeure provision, a party can still be released from liability if it proves that the event:

• was unforeseeable; • was beyond its control; and • made performance impossible. 6.3 Concept of Hardship

Under Moroccan law, there is no general legal principle that automatically grants a party the right to amend or renegotiate a commercial contract on the ground of substantial hardship, when no specific clause exists. The DOC is based on the principle of pacta sunt serv - anda (Article 230), and states that “legally formed agreements have the force of law for those who have made them and may only be revoked by mutual con - sent or for causes authorised by law”. This principle means that contracts remain binding even if perfor - mance becomes more difficult or costly, as long as it is not impossible. That said, in the private commercial sphere, hardship is not recognised by default. The only way for a party to secure a right to renegotiate or modify the contract in the case of hardship is to include a specific contrac - tual clause (a “hardship” or “renegotiation” clause). 6.4 Hardship Clauses It has become common practice for long-term com - mercial contracts to include a hardship clause allow - ing the parties to renegotiate or amend the contract if unforeseen events substantially alter its economic balance. However, Moroccan law does not recognise a statu - tory right of renegotiation in such situations. The prin - ciple of pacta sunt servanda requires contracts to be performed as agreed, even if performance becomes more onerous. Therefore, in the absence of a hardship clause, a party cannot rely on Moroccan law to seek amendment or renegotiation due to hardship.

301 CHAMBERS.COM

Powered by