SINGAPORE Law and Practice Contributed by: Andrew ANG, Audrey CHNG, CHAN Jia Hui and SOONG Wen E, WongPartnership LLP
• vicarious liability; ie, employers are strictly liable for wrongful acts of their employees committed in the course of employment, even if the employer was not at fault; • breach of statutory duty (if the statute imposes absolute obligation); and • breach of trust/fiduciary duties, which can be strict for accounting of unauthorised gains. Criminal or regulatory statutes also contain numerous strict liability offences or breaches, eg, in the areas of environmental protection, workplace safety, food safety and public health, road traffic, data protection, financial regulation, to name a few. In most of these, proof of intent or negligence is not required, though the offending party may be able to avail itself of statu - tory defences. 5.4 Contractual Limitation on Liability Singapore law generally allows parties the freedom to contract and to allocate risk as they deem fit. It follows that a clearly drafted contractual limitation of liability is generally enforceable under Singapore law, provided that it does not offend statutory controls (primarily, UCTA reasonableness) and public policy (eg, exclu - sion of liability for fraud). Under UCTA, an exemption of liability clause for negli - gence or breach of contract and indemnity clauses in respect of liability that may be incurred for negligence or breach of contract must satisfy the requirement of reasonableness. UCTA generally applies more stringently in cases where one party deals as consumer or on the other’s written standard terms of business; eg, Section 3, which imposes the reasonableness requirement on exclusion or restriction of liability clauses for breach of contract, only applies when this is the case. Also see 3.4 Application of Local Law on Standard Terms on the application of the contra proferentem rule to standard terms; even if valid under UCTA, exclu - sion and limitation clauses are construed strictly and ambiguities interpreted contra proferentem against the drafter. It follows that it makes a material differ - ence whether the respective clause is a standard term or is individually negotiated. Singapore courts would tend to uphold such clauses more willingly if
they were individually negotiated clauses between sophisticated parties or commercial entities of equal bargaining power.
6. Force Majeure and Hardship 6.1 Concept of Force Majeure
There is no free-standing common law force majeure concept under Singapore law. Force majeure oper - ates only if the contract provides expressly for it. If the contract is silent, relief only arises under the doctrine of frustration under common law and under the FCA. The common law frustration principle holds that a con - tract is frustrated when, after it was made, an event occurs without the fault of either party that makes performance impossible or renders it radically differ - ent from what the parties originally agreed. If frustra - tion can be established, the contract is automatically discharged and both parties released from further performance obligations. It is insufficient to establish frustration if the event merely increases costs, delays performance or makes it less profitable. The event must also be truly outside the parties’ control. To establish frustration success - fully, parties should be prepared to demonstrate that they made diligent efforts to perform notwithstanding the event (eg, pursuing substitutes, practicable rerout - ing, reasonable contingency measures, etc). Once frustration is established, the FCA provides for the adjustment of the losses and benefits between the parties, subject to the court’s discretion (apart from limited cases, eg, charterparties, which are excluded under the FCA). Notably, if a force majeure clause is contained in the contract, it can exclude or modify the application of the frustration doctrine and tailor the relief. 6.2 Force Majeure Clauses It is fairly standard practice in Singapore commercial contracts (particularly in the areas of construction, energy and infrastructure, supply or manufacturing agreements, shipping, trade and logistics) to include
358 CHAMBERS.COM
Powered by FlippingBook