SINGAPORE Law and Practice Contributed by: Andrew ANG, Audrey CHNG, CHAN Jia Hui and SOONG Wen E, WongPartnership LLP

a force majeure clause or relief from performance clause. The clause would: • define the events (eg, acts of God, government actions, epidemics, supply chain disruptions, etc) (as well as any events which parties agree to spe - cifically exclude from the application of the clause); and • specify notice and mitigation requirements, and consequences on the contract such as suspen - sion, extension and/or termination. Absence of such a clause does not bar relief under frustration, but the threshold for frustration is higher and narrower. Please also see 6.1 Concept of Force Majeure . 6.3 Concept of Hardship There is no general doctrine akin to civil law hardship or the doctrine of imprévision (allowing for renegotia - tion of the contract in the event of fault-free unforesee - able change in circumstances resulting in excessive burden for one party) under Singapore law. Singapore courts will not rewrite a bad bargain for mere hardship or economic change. Parties are expected to allocate risk expressly through their negotiations, eg, through price-adjustment, indexation and/or material adverse change clauses. Relief can be obtained only if force majeure (within the language of the force majeure clause in the contract) or frustration can be estab - lished. Also see 6.1 Concept of Force Majeure and 6.2 Force Majeure Clauses . 6.4 Hardship Clauses The inclusion of a hardship clause is not standard practice in all commercial contracts given that such a clause would add uncertainty and lack of finality to the parties’ bargain, though such a clause is more com - monly included in long-term supply/offtake, construc - tion/infrastructure, energy/commodities and logistics contracts, with an international element, and where exposure to price volatility and risk is significant. The language of the clause and its scope are likely to vary with individual cases and depend on the parties’ bar - gaining positions and commercial expectations. The hardship clause may provide for notice, renegotia - tion, expert determination, price review or adjustment mechanics, price indexation, suspension and/or ter -

mination in the event of “hardship”, which the clause should define. It may also be limited to a good faith consultation obligation, which would have limited sub - stantive effect. In the absence of such a clause, there is no statutory or common law right to renegotiate. A force majeure or termination clause in the contract could be relied on, or a specific price-adjustment trig - ger clause, rather than a general hardship provision. 7. Warranties and Remedies 7.1 Warranties and Remedies Under Local Law As a preliminary general overview, Singapore law dif - ferentiates between conditions and warranties. The Singapore Court of Appeal case of RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and another [2007] SGCA 39 sets out the situations entitling an innocent party to terminate the contract at common law. These include: if there is an express termination right, if the party in breach renounces the contract, if a condition (as opposed to a warranty) is breached, and (follow - ing the approach under the seminal English Court of Appeal decision of Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26) if a breach has been committed, the consequences of which will deprive the innocent party of substantially the whole benefit which it was intended it should obtain from the contract. Additional to the right of termination, other potential remedies for breach of contract include the following: • Damages (see 5.1 Concept of Liability for a sum- mary of the measure of damages). • Debt claims. • Liquidated damages: These are enforceable if they are not penal. To determine whether the clause is a penalty or not, as mentioned in the Denka Advan- tech case discussed in 1.5 Significant Court Deci - sions or Legal Developments , the applicable test in Singapore remains the statement of principles set out in the Dunlop Pneumatic Tyre case. The penalty rule applies only in the context of a breach of contract, and turns on whether the contractual provision concerned provided a genuine pre-esti - mate of the likely loss at the time of contracting.

359 CHAMBERS.COM

Powered by